Wada-Asso of mortar pump force feed construction

The standard construction plan

Light construction plan

Light construction plan with dynamo


Details of Light construction plan with dynamo

Integrated piping length within 40m. Height vertical within 20m. Depth vertical within 10m. Amount of total force feed within 10m^3.
(The piping fixation part of about 3m interval in the work stand etc. isnecessary for the vertical direction.)

The business area: Tokyo, Kanagawa, Chiba, and Saitama. (Area that can reach on general road)
Working hours: AM 7:00 - PM 5:00  (The installation time and the removal time are included).

Cash fee on weekday: Basic fee(Please inquire.) + 10000 yen (including tax).
Cash fee on Sunday/national holiday: 10% surcharge of Basic fee + 11000 yen (including tax).
Cash fee on Night work: 50% surcharge of Basic fee + 15000 yen (including tax).

The cash fee of the cancellation on that day

Before laying pipes 30000 yen (including tax).
After laying pipes 40000 yen (including tax).
After setting up the pump 100% of fee.

Customers need to be prepared(Excluding the fee).


1: The place where the track is put becomes indispensable from the mortar pump within 30m. 

The electric wire must prepare the place not stepped on by the car etc.

2: Tap water of water service.

Volumes of water are necessary.

3: Cement is one usual bag (It is not deteriorated).


4: Installation location of mortar pump of about 5 - 6m^2.


5: Protection material.  Mortar splashes by 3-4m of the surrounding of the mortar pump. It is necessary to protect it.

It is necessary to protect the vicinity of piping and the vicinity of the construction place.

6: Number of workers necessary for work.

The operator who accompanies the lease is only one person.
In work for which the number of people is necessary, the worker is separately necessary.

7: Prepare a considerably soft mortar.

The agitator is not installed in the mini hopper.
Therefore, please prepare a considerably soft mortar.